Note that External Works is undergoing further refinements. More updates will be released in future COP versions.
Key Gateways | Objective | Road alignment details to be prepared (other details to be prepared and submitted as required) | Supporting Information required |
---|---|---|---|
Pre-DG (Land Use, TCOT, PAFS, TIA) | To establish RRL and development boundary |
|
|
Pre-Submission, Planning and Other Consultations | To seek clarifications for details to be submitted at DG stage | As required by Agency / QP to seek clarification from LTA |
|
Design Gateway (G1) | To establish development platform level and development access that will properly interface with the proposed carriageway |
|
|
Piling Gateway (G1.5) (Optional) | Piling gateway also includes earth retaining structures (slope, retaining wall, CBP etc.) within the road reserve | - | - |
Construction Gateway (G2) | To finalise all other details necessary for construction of the road and related infrastructure works |
| - |
Independent Submissions | To finalise individual agency requirements after construction gateway that do not have any impact on other agencies requirements | Approval to commence engineering works/restricted activities within the Railway Protection Zone | - |