3-Gateway Process
G | Gateways | Objectives | Key Approvals |
---|---|---|---|
- | Pre-Submission, Planning and Other Consultations | To seek one or more agencies' guidance and/or waivers on a project's submission requirements before making a formal submission | -
|
G1 | Design Gateway (DG) For Design Parameters | To resolve multi-agency key parameters which have impact on design parameters and client’s brief, before proceeding to detailed design. | • URA PP • LTA, NEA and PUB DC Clearances • NParks DC Approval |
G1.5 | Piling Gateway (PG) *optional | To resolve requirements pertaining to piling and foundation works (e.g. pile caps, raft foundation, earth retaining and stabilising structures), excluding superstructural works. | • BCA ST Approvals for Permanent Piling Works • LTA RPZ AIP for Pile Design and Pile Layout Plan |
G2 | Construction Gateway (CG) | To resolve multi-agency requirements concerning design details that need to be coordinated before commencement of main structural works and launch of Sales. | • URA WP • BCA BP and ST Approvals • LTA Street Plan Clearance, BP (Parking), BP (Rails) • NEA and PUB BP Clearance Certificate • SCDF BP Approval |
- | Independent Submissions (IDP) *if applicable | To clear agency-specific requirements with no cross-agency dependencies (i.e. typically affecting only one relevant agency). E.g. structural submission of ancillary structures such as barriers/ claddings to BCA | • NParks Tree Felling Approval • PUB Earth Control Measures Approval |
G3 | Completion Gateway (TOP) Application for TOP/CSC | To document “As-Built” plans and obtain Occupancy Permit/ Statutory Completion
| - |
For simpler projects, please refer to the Direct Submission Process (DSP) here. |
Example of a project making regulatory submissions across CORENET X Gateways
An example of an independent submission for Structural works is as follows.
List of independent submissions under CORENET X and their corresponding service level agreement
(updated in July 2024)
Agency | Independent Submission under CORENET X | Service Level Agreement (i.e. expected response time) |
BCA | Structural design with design calculations of independent work/ structures e.g. demolition, temporary ERSS, cladding, barriers, temporary traffic decking Building design details of specialised works such as Environmental Sustainability (ES) regulatory detailed requirements Constructability score submission (C-score) | 15 working days |
LTA | Railway protection/ road structure protection details for engineering works/ restricted activities apart from aspects cleared in PG/CG: | 20 working days |
NEA | -Temporary sanitary facilities at construction site | 20 working days |
NParks | -Planting/ landscaping scheme of planting areas within development, including open air parking areas at street level, of green verges along roadside (i.e. number and species of trees and plants to be planted) | 20 working days |
PUB | Application to work in public sewerage system ("Form B") | 14 working days |
-Notification of Water Service Installation (WSI) works by Professional Engineer (PE) involving pumping equipment of water tank (site plans, water reticulation schematic/ layout drawing of WSI design works, water requirements, SP Water Utilities Account Number) | 21 working days | |
SCDF | Fire Protection (FP) and Mechanical Ventilation (MV) Plans: Independent Building Plan (BP) submission (e.g. A&A, change of usage, petroleum and flammable material (P&FM) storage, etc.) not involving other agencies Temporary Fire Permit (TFP)/ Fire Safety Certificate (FSC) | 5 working days |
Minor addition/ alteration (MAA) | Approval via lodgment | |
URA | Strata/ land subdivision and amalgamation (if applicable) | Approval via lodgment |